Work close to wrapping up on two of three building renovations

North Hall, Price Commons to reopen in fall; Bowman Hall project continues
A worker in a lift repairs a section of the historic Bowman Hall Clock Tower on Tuesday, Aug. 6, at UW-Stout. / UW-Stout photos by Chris Cooper
​Jerry Poling | August 12, 2019

With less than a month to go before fall semester classes, renovations are close to wrapping up at two University of Wisconsin-Stout buildings.

North Hall and Merle M. Price Commons, adjacent buildings whose east sides open to the campus mall and west sides face Broadway Street, will reopen around the end of August.

Workers in lifts repair bricks more than 100 feet up on the Clock Tower. The project includes putting a new copper roof on the tower.Students are scheduled to move into residence halls, including North, on Sunday, Sept. 1. Classes begin Wednesday, Sept. 4. North Hall has undergone a complete renovation, along with three small additions and a new main entryway.

At Price, work has been limited to the first floor, exterior and entryways. The second floor, housing the main student cafeteria, previously was remodeled.

A third campus project, on the exterior of historic Bowman Hall, will continue into the fall and likely resume next spring. It involves replacing 30,000 bricks, stone accents and supports, and brick mortar and windows throughout. Also, the 135-foot Clock Tower will get a new roof and structural repairs.

The only interior work at Bowman, renovation of the south side extension that houses Registration and Records, wrapped up earlier this year. Original brick walls and beams were exposed.

The three projects, which began in spring 2018, total more than $38 million.

The renovation of North Hall includes this new entryway on the west side.

 

North Hall

Workers are putting the finishing touches on the exterior of the building, including the new ground-level east entry, finishing and furnishing the interior and landscaping.

The $21.74 million project, funded with student fees, includes all new student rooms, bathrooms, common areas, entries and infrastructure. Built in 1967, the building has expanded 14,000 feet to about 90,000 square feet. It will house about 370 students.

“The bathrooms were moved to the outer edges of the building, opening it up in the middle for lounges. It’s much brighter,” said Mike Bowman, project manager for Facilities Management.

Price Commons

Also built in 1967, Price Commons has new windows and sills, a refurbished patio on the west side and some new bricks, along with expanded entryways on all sides.

The new first floor will feature refurbished offices for the LGBTQ center, the Qube, and an expanded and updated lounge that opens to the patio. The Qube reopened in April.

“It’s going to be a beautiful building. When you walk in the east side, you’ll be able to see all the way to the west side. Before, it was closed off. This will help brighten it up a lot,” Bowman said of the $7.57 million project, also funded with student fees.

Renovation of the first floor and exterior aspects of Merle M. Price Commons at UW-Stout is nearly complete.

 

The new patio “will be much more inviting for students,” he added.

The first floor also houses student support offices, such as the Campus Card Office, University Dining and University Housing.

Bowman Hall

Much of the work grinding out and replacing the mortar between bricks has been done, as has replacing the windows — to the original full openings — and stone.

The new bricks, stone and windows are historically accurate, overseen by an architect hired by the state. Bowman Hall, in the National Register of Historic Places, was built in 1897 by school founder James Huff Stout. It mostly houses student support offices as well as some classrooms.

The last major aspect of the $8.95 million renovation will be structural steel and other repairs to the tower and replacing the copper roof. The quill weathervane on the roof will be restored. Depending on the fall weather, the work may wrap up next spring.

The bells in the Clock Tower, which ring every quarter hour, were silenced in late May as work began on the tower area. They have rung for special occasions. Regular bell chimes could resume in October.

In a small separate project, the timing mechanism for the four clock faces in the tower isn’t working properly and will be repaired.

###

Photos

Workers in lifts repair bricks more than 100 feet up on the Clock Tower. The project includes putting a new copper roof on the tower.

The renovation of North Hall includes this new entryway on the west side.

Renovation of the first floor and exterior aspects of Merle M. Price Commons, seen from the east side, is nearly complete.

 


Invitation to innovation: Special spring events celebrate students’ creativity, scholastics Featured Image

Invitation to innovation: Special spring events celebrate students’ creativity, scholastics

Destination Weekend, April 5-6, features Fashion Without Fabric, ‘Dogfight’ musical and more for campus and community
PHOTO ESSAY: Two Classes Work with Children a World Apart Featured Image

PHOTO ESSAY: Two Classes Work with Children a World Apart

Discover what Sociology and Education students learn on location in Thailand and Cozumel
It’s More than a Package: UW-Stout packaging program to host international student-led conference Featured Image

It’s More than a Package: UW-Stout packaging program to host international student-led conference

Pack Jam invites industry, alumni, community to see fresh ideas April 7-9